Sunday, November 14, 2010

Build Day 61-70

The Ensuite is commisioned! We now have a fantastic new ensuite with all the bells and whistles.
The other internals are really starting to take shape. The old bathrom was removed and a new floor, wall and ceiling framing, was install in 2.5 days. Just amazing.

16 November:
1. Cabinet maker is coming to measure for the kitchen and media cabinet
2. Electrician to wire for kitchen, bathrooms and laundry
3. Plumber for kitchen, laundry , bathroom

17 November
1. Gyprock sheeting for all new areas

6-9 December
1. Floor boards to be polished with semi-gloss







No comments: